Bed making Phase 2
The bed making starts with marking of soil and wetting it properly so that it can be dug according to the size needed ..
Each bed is 2feet wide and about a feet and a half high and there is a gap of 1 ft walking distance ..
Water was one of the biggest hurdle here.. we needed soo much of water suddenly and we were not informed of it before the workers from pune landed.. so we had to rush in and search for water tankers to get water from the near by water sources .. awwwww.. it was such a pain ... power cuts .. machines problems .. pipe line problems .. ..if only i knew it earlier would have been a lot easier in arranging for the water ..
anyways it was delay by two days due to the water issue. then the work started off.. bed making starts with marking and digging up the soil and making beds... regular wetting with piper while working was very important .. a plank was used to finish the borders neat and in shape...
It will take another 2 days more for the beds to be ready i guess and then the drip line will be added to it ...
if see closely the foggers are also connected in half of the farm in the meanwhile when the water issue was going on .. anyways it will be continued after bed making and will post more pics of them laters.,,,








Each bed is 2feet wide and about a feet and a half high and there is a gap of 1 ft walking distance ..
Water was one of the biggest hurdle here.. we needed soo much of water suddenly and we were not informed of it before the workers from pune landed.. so we had to rush in and search for water tankers to get water from the near by water sources .. awwwww.. it was such a pain ... power cuts .. machines problems .. pipe line problems .. ..if only i knew it earlier would have been a lot easier in arranging for the water ..
anyways it was delay by two days due to the water issue. then the work started off.. bed making starts with marking and digging up the soil and making beds... regular wetting with piper while working was very important .. a plank was used to finish the borders neat and in shape...
It will take another 2 days more for the beds to be ready i guess and then the drip line will be added to it ...
if see closely the foggers are also connected in half of the farm in the meanwhile when the water issue was going on .. anyways it will be continued after bed making and will post more pics of them laters.,,,
Bed making stage 1
Making of beds is one of the important steps in a achieving a good crop. As mentioned in the previous posts, the vermicompost, rice husk and soil have been throughly mixed and rotovated with a blade so that it pulverised and mixed properly.
Then the whole of the farm is made wet with excess of water and then let it come back to the Vapsa condition. After the vapsa condition is brought back it is rotovated with a tiller one last time and then the soil is ready for bed making .....
Then the whole of the farm is made wet with excess of water and then let it come back to the Vapsa condition. After the vapsa condition is brought back it is rotovated with a tiller one last time and then the soil is ready for bed making .....
Sunday, April 3, 2011
Layering with Vermicompost and Rice Husk ..
The top layer of the soil bed is now being filled with Vermicompost and then with a fine layer of husk.
Ideally we need to take about 35% of bed with vermicompost or FYM..... 55-60% red soil 4kg/m2 rice husk and about 5% sand if soil is not very loose.!!
we used about 100tonnes of vermicompost and it has been a very labor intensive process to get it from the company. Though we used so much it just did not make even a good size layer at least. Nvertheless i will add a lil more after plantation directly on the bed.
then i got couple of trucks of rice husk from a rice mill near by and got it dumped inside.. will have to layer it out with a dozer tomorrow or so .
Ideally we need to take about 35% of bed with vermicompost or FYM..... 55-60% red soil 4kg/m2 rice husk and about 5% sand if soil is not very loose.!!
we used about 100tonnes of vermicompost and it has been a very labor intensive process to get it from the company. Though we used so much it just did not make even a good size layer at least. Nvertheless i will add a lil more after plantation directly on the bed.
then i got couple of trucks of rice husk from a rice mill near by and got it dumped inside.. will have to layer it out with a dozer tomorrow or so .
| First the soil is to be layered .. properly.. |
| Vermicompost dumped in random |
| vermicompost tends to dry up very soon.. so its better to water it once in awhile until its mixed up with soil. |
| Husk layered on the right side.. |
Thursday, March 17, 2011
Soil filling and the levelling works on the go !!
The soil filling was done after all the rocks were unearthed and pushed out with a JCB and then we had to pump in about 160 truck loads of red soil from another village nearby. The soil quality was good and we had to pay about 1300rupees for each truck load... i know thats lot of money for soil but then soil is the most important thing for the well being of the plants .. so i didnt want to compromise on this one ..or .even in the next step in soil preparation which is adding FYM or Vermicompost. we will be adding vermicompost today or tomorrow on this soil .. i am thinking of adding about 10 -12 tonnes of it
Water works - Tank/ sump construction.
![]() |
| After the intial filling with cement and large sized gravel on the floor the walls work started off.. |